Present Installed Generation Capacity (MW) as on 30 November, 2021.
Public Sector
|
No of Power Plant
|
Installed Generation Capacity (MW)
|
BPDB
|
38
|
6013
|
APSCL
|
5
|
1444
|
EGCB
|
3
|
957
|
NWPGCL
|
7
|
1401
|
B-R Power gen
|
1
|
149
|
RPCL
|
3
|
182
|
Subtotal
|
57
|
10,146 (46%)
|
Joint Venture
|
|
|
BCPCL (JV of NWPGCL & CMC, China)
|
1
|
1244
|
Subtotal
|
1
|
1244 (6%)
|
Private Sector
|
|
|
IPPs
|
59
|
8042
|
SIPPs (BPDB)
|
4
|
99
|
SIPPs (REB)
|
9
|
251
|
15 YR. Rental
|
4
|
169
|
3/5 YR. Rental
|
12
|
920
|
Subtotal
|
88
|
9481 (43%)
|
Power Import
|
|
|
Bheramara HVDC
|
|
1000
|
Tripura
|
|
160
|
Subtotal
|
|
1160 (5%)
|
TOTAL
|
146
|
22,031*
|
*Including Captive Power & Off Grid Renewable Energy Total Installed Capacity (22,031+2,800+404) =25,235MW
MAXIMUM DEMAND SERVED FAR
|
13,792 MW
|
27-04-2021
|
TRANSMISSION LINES (400 kV) |
861 Ckt. K.M |
FY-2020 |
TRANSMISSION LINES (230 kV)
|
3658Ckt. K.M
|
FY-2020
|
TRANSMISSION LINES (132 kV)
|
7677Ckt. K.M
|
FY-2020
|
GRID SUB-STATION CAPACITY (400/230 kV) |
3770 MVA |
FY-2020 |
GRID SUB-STATION CAPACITY (400/132 kV) |
1300 MVA |
FY- 2020 |
GRID SUB-STATION CAPACITY (230/132 kV)
|
13,075 MVA
|
FY- 2020
|
GRID SUB-STATION CAPACITY (132/33 kV)
|
25,624 MVA
|
FY- 2020
|
DISTRIBUTION LINES (33 KV & BELOW) (only BPDB)
|
33,640 K.M
|
FY-2020
|
CONSUMER NUMBER (BPDB)
|
32,36,802
|
FY-2020
|

PRIMARY GRID SYSTEM OF BANGLADESH
(As on June, 2017)
(Click here for download Grid Map as pdf format.)

|